CIA-2 - Engagement Planning - Section A.4

Determine the appropriate approach for an engagement, evaluating agile, traditional, integrated, and remote auditing methods and applying project management concepts.

Evaluate agile, traditional, integrated, and remote auditing approaches against an engagement's objectives, resources, and constraints to select the most suitable method. Apply project management concepts such as scoping, sequencing, and resource allocation to plan and conduct the engagement efficiently regardless of the approach chosen.

Agile auditingIntegrated auditingProject management

Practice question for this objective

Free sampleEngagement Planningmedium

A new internal auditor is applying project management concepts to a six-week compliance engagement. Two testing tasks depend on receiving a data extract that the IT team can only deliver in week three. To keep the engagement on schedule, what should the auditor do when building the plan?

  • AIdentify the dependency, schedule independent tasks earlier, and sequence the data-dependent tests after the week-three delivery. Correct
  • BAssume the extract will arrive in week one and schedule all testing to start then, adjusting only if it slips.
  • CReport to the audit committee that the engagement cannot be completed within six weeks because of the IT constraint.
  • DRemove the two data-dependent tests from scope so the engagement avoids relying on the IT extract at all.
Applying project management to an engagement means mapping task dependencies and sequencing work so constraints are absorbed rather than allowed to derail the schedule. Sound scheduling identifies which tasks depend on others, runs independent work in parallel, and orders dependent tests after their inputs arrive, keeping the critical path intact without dropping scope or escalating prematurely.

Why A is correct: Recognising the dependency and reordering work so independent tasks proceed while data-dependent tests follow the extract is exactly how project sequencing protects the timeline.

Why B is wrong: Assuming an earlier delivery than IT has confirmed builds the schedule on a false premise, so slippage is almost guaranteed rather than managed.

Why C is wrong: Escalating a manageable scheduling constraint as a blocker is premature, since the plan can absorb the dependency through sequencing rather than declaring failure.

Why D is wrong: Cutting necessary tests to dodge a dependency narrows coverage and may leave the objective unmet, trading schedule comfort for a weaker engagement.

See more CIA-2 practice questions, answers explained.