ITIL-4 domain - 18% of the exam

Know the purpose and key terms of 15 ITIL practices

Know the purpose and key terms of 15 ITIL practices is 18% of the ITIL-4 exam. These are the objectives it covers, each with practice questions, with every answer explained.

The domain in numbers

50
Practice questions
2
Objectives
24
Easy
26
Medium

Where people go wrong

  • Swapping deployment management and release management

    The wrong answers reverse the two practices, or fold them into one. Deployment management moves new or changed components, such as software, hardware and documentation, into live or other environments. Release management makes new and changed services and features available for use. A feature can sit deployed on production servers and stay switched off, so the move and the go-live are separate steps handled by different practices.

    See it in a sample question
  • Defining change enablement by a neighbouring practice

    The wrong answers describe change enablement using the purpose of another practice: moving components to live, making features available, resolving incidents, or protecting information. Others treat it as a brake that blocks changes. Its purpose is to maximise the number of successful service and product changes by ensuring risks are assessed, changes are authorised and the change schedule is managed. It enables change safely rather than restricting it.

    See it in a sample question
  • Treating a configuration item as an IT asset

    The wrong answers treat the two terms as the same thing, or pick one by the type of component. A configuration item is any component that needs to be managed in order to deliver an IT service. An IT asset is any financially valuable component that can contribute to delivering an IT product or service. A leased router with little resale value is still a configuration item, and a valuable licence is an asset.

    See it in a sample question
  • Mixing up event, incident, problem and known error

    The wrong answers hand each term the definition of its neighbour. An event is any change of state that has significance for managing a service or configuration item, such as a disk-usage threshold being crossed while nothing has failed. An incident is an unplanned interruption or reduction in the quality of a service. A problem is a cause, or potential cause, of one or more incidents. A known error is a problem that has been analysed but not resolved.

    See it in a sample question

Objectives in this domain

Sample questions from this domain

Free sampleKnow the purpose and key terms of 15 ITIL practicesmedium

At Orion Media, a new version of the billing application has been moved onto the production servers, but the team has deliberately kept the new invoicing feature switched off until finance signs off next week. Which pairing correctly matches these two activities to their ITIL 4 practices?

  • AMoving the code to production is deployment management; switching the feature on for users is release management. Correct
  • BMoving the code to production is release management; switching the feature on for users is deployment management.
  • CBoth activities belong to deployment management, since each one touches the live production environment directly.
  • DBoth activities belong to release management, since each one concerns delivering a new version of the application.
Distinguish deployment management (moving components into an environment) from release management (making features available for use). ITIL 4 separates these on purpose: deployment management is concerned with moving new or changed components to live or other environments, whereas release management is concerned with making new and changed services and features available for use. Deploying code with a feature toggled off shows a deployment can occur before a release.

Why A is correct: Correct: deployment management moves new or changed components into an environment such as production, while release management makes new or changed features actually available for use, so the sign-off switch-on is a release activity.

Why B is wrong: Tempting because both terms sound interchangeable, but this reverses them: making a feature available is release, not deployment, and moving components into an environment is deployment, not release.

Why C is wrong: Tempting because both activities involve production, but ITIL 4 deliberately separates moving components (deployment) from making features available for use (release), so collapsing them into one practice is wrong.

Why D is wrong: Tempting because a new version is involved, but physically moving components into an environment is deployment management, so treating the whole thing as release ignores the distinction ITIL 4 draws.

Free sampleKnow the purpose and key terms of 15 ITIL practicesmedium

In ITIL 4, which statement most precisely describes the purpose of the change enablement practice?

  • ATo move new and changed hardware, software, and other components into live environments so that they are available for use as agreed.
  • BTo make new and changed services and features available for use, coordinating the point at which functionality is released to users.
  • CTo maximise the number of successful service and product changes by ensuring that risks are properly assessed, changes are authorised, and a change schedule is managed. Correct
  • DTo ensure that accurate and reliable information about configuration items and their relationships is available when and where it is needed.
Recall that change enablement exists to maximise successful changes by assessing risk, authorising, and scheduling them. Change enablement is the authorisation-and-scheduling gate: it weighs the benefit of a change against the risk to users and the business, so its defining purpose is safe, authorised, well-scheduled change rather than the physical act of building, releasing, or deploying anything.

Why A is wrong: Tempting because moving components into live environments is a core delivery activity, but this describes the deployment management practice, not change enablement, which is concerned with authorising and scheduling change.

Why B is wrong: Tempting because it sounds like a change reaching users, but this is the purpose of release management, which governs when functionality becomes available, whereas change enablement governs whether the change is authorised at all.

Why C is correct: This matches the ITIL 4 purpose of change enablement: it balances the need to make beneficial changes against the need to protect customers and users from the adverse effects of change through risk assessment, authorisation and scheduling.

Why D is wrong: Tempting because configuration data supports change decisions, but this is the purpose of service configuration management; change enablement uses that information rather than being defined by maintaining it.

Free sampleKnow the purpose and key terms of 15 ITIL practiceseasy

During an audit at Penhurst Council, an analyst, Ravi, must catalogue every component that has financial value and could contribute to delivering an IT service, including staff laptops and purchased software licences. Which ITIL 4 term describes the items Ravi is recording?

  • AConfiguration items, because any component recorded for service delivery is a configuration item
  • BChanges, because adding items to a central catalogue modifies the environment
  • CEvents, because each item is logged as it is discovered during the audit
  • DIT assets, because an IT asset is any financially valuable component that can contribute to delivering an IT product or service Correct
An IT asset is any financially valuable component that can contribute to the delivery of an IT product or service. IT assets are defined by their financial value and their potential to contribute to delivering an IT product or service, which is why a catalogue of valuable laptops and licences records assets rather than configuration items, changes or events.

Why A is wrong: Tempting because laptops and licences are frequently recorded as configuration items too, but a configuration item is defined by needing to be managed to deliver a service, not by having financial value.

Why B is wrong: Tempting because cataloguing feels like altering records, but a change is the addition, modification or removal of anything that could affect services, not the valuable components being listed.

Why C is wrong: Tempting because logging resembles event detection, but an event is a change of state significant to service management, not a financially valuable component.

Why D is correct: Correct: ITIL 4 defines an IT asset as any financially valuable component that can contribute to the delivery of an IT product or service, which fits the laptops and licences Ravi is cataloguing by value.

Free sampleKnow the purpose and key terms of 15 ITIL practiceseasy

At Larkfield Media, a monitoring tool automatically logs that a database server's disk usage has crossed a defined threshold and raises a notification for the operations team to review. Nothing has failed and no service has slowed. In ITIL 4 terms, what has the monitoring tool detected?

  • AAn incident, because a monitored metric has breached its defined threshold
  • BA problem, because a threshold breach reveals an underlying cause of incidents
  • CAn event, because it is a change of state that has significance for the management of a configuration item or service Correct
  • DA change, because the level of disk usage has been modified
An event is any change of state significant to the management of a service or configuration item, usually raised as a notification. A monitoring tool flagging a threshold breach identifies a change of state significant to managing a configuration item or service, which is precisely the ITIL 4 definition of an event; because no service has been interrupted or degraded, it is not an incident.

Why A is wrong: Tempting because thresholds relate to service targets, but an incident is an unplanned interruption or a reduction in the quality of a service, and here nothing has been interrupted or degraded.

Why B is wrong: Tempting because monitoring can help find problems, but a problem is a cause, or potential cause, of one or more incidents identified through investigation, not a single detected state change.

Why C is correct: Correct: ITIL 4 defines an event as any change of state that has significance for the management of a service or configuration item, typically recognised through a notification, which is exactly what the monitoring tool has raised.

Why D is wrong: Tempting because the phrase change of state sounds like a change, but a change is the deliberate addition, modification or removal of something that could affect services, not an observed state detected by monitoring.