During the daily scrum for the Larkspur analytics team, a developer says she is blocked because a shared test environment keeps failing. What is the scrum master's most appropriate response?
- ANote the impediment and work after the event to help remove it, for example by engaging the team that owns the environment. Correct
- BTake over the daily scrum and assign each remaining task to a specific developer so the plan is clear.
- CTell the developer to raise the problem in the sprint retrospective in two weeks so it can be discussed properly.
- DRecord the blocker in the product backlog as a defect item for the product owner to prioritise next sprint.
Why A is correct: Removing impediments that block the developers is a core scrum master service, and doing so outside the timeboxed event keeps the daily scrum focused on the developers' plan.
Why B is wrong: The daily scrum is the developers' event to plan their own work, so taking control and handing out assignments undermines the team's self-management.
Why C is wrong: Deferring an active blocker to the retrospective is tempting because retrospectives cover improvements, but it leaves the impediment unresolved for the rest of the sprint.
Why D is wrong: A blocking environment issue is an impediment to remove now, not a backlog item to schedule later, so filing it away delays resolution and misreads the scrum master's role.