Foundational project management knowledge across predictive, agile, and business analysis approaches for the PMI CAPM examination, with every answer explained, right and wrong.
Exam domains and weighting
The CAPM blueprint is split across 4 domains. See the official exam guide for the authoritative breakdown.
Free sample questions
No account needed. Every question explains why every answer is right or wrong, just like the full bank.
lock_openFree samplePredictive, Plan-Based Methodologieshard
A small project network has five activities. Activity A (3 days) and Activity B (6 days) both start the project. Activity C (8 days) follows A. Activity D (4 days) follows B. Activity E (5 days) starts only after both C and D finish, and E ends the project. Which path is the project's critical path?
- AA to C to E, with a total duration of 16 dayscheck_circle Correct
- BB to D to E, with a total duration of 15 days
- CA to C to E, with a total duration of 11 days
- DB to D to E, with a total duration of 18 days
The critical path is the longest continuous path through the network, which determines the earliest possible project finish. Adding activity durations along each complete path gives A to C to E at 16 days and B to D to E at 15 days. The longest of these, 16 days, is the critical path because any delay to its activities delays the whole project.
Why A is correct: The critical path is the longest continuous path through the network. A to C to E sums to 3 plus 8 plus 5, which is 16 days, longer than the only other path B to D to E at 15 days, so it sets the earliest project finish and its activities have zero total float.
Why B is wrong: B to D to E is the near-critical path at 15 days and carries only 1 day of total float. It is tempting because it starts with the longest single activity, B at 6 days, but a longer path exists, so it is not critical.
Why C is wrong: This correctly names the longest path but miscalculates its length, most likely by dropping activity E from the sum. The path A to C to E actually totals 16 days, not 11, so the duration stated here is wrong.
Why D is wrong: This selects the near-critical path and also overstates its length, probably by adding an activity that is not on it. B to D to E totals 15 days, and in any case it is not the longest path, so it is not the critical path.
lock_openFree sampleAgile Frameworks/Methodologiesmedium
The Meridian mobile-banking team has a signed 40-page requirements document, but during the first two-week iteration the client watches the working login flow and asks for three material changes. The team lead argues that the contract fixes the scope and the changes should wait for a formal change request. Which position best reflects the values of the Agile Manifesto?
- ADefer the changes to a later release, because the signed requirements document is the team's contract and must govern the current iteration.
- BWelcome the client's changes now, because responding to change is valued over following a fixed plan when it delivers a better product.check_circle Correct
- CReject the changes outright, because customer collaboration tends to matter most at the start of the project when the scope is first agreed.
- DAccept the changes only after the client raises a formal written change request through the document-control process.
The Agile Manifesto values responding to change over following a plan when adaptation yields a better outcome for the customer. Agile treats requirements as emergent; feedback from a working increment is a signal to adapt, and the Manifesto explicitly ranks responding to change above following a fixed plan, which is why welcoming the change is the best position.
Why A is wrong: This treats comprehensive documentation and the plan as fixed authority, which inverts the Manifesto value that prioritises responding to change, so it is wrong.
Why B is correct: The Manifesto value 'responding to change over following a plan' supports adapting to the emerging requirement rather than deferring to the original scope document, so this is correct.
Why C is wrong: It is tempting because early scoping does matter, but the Manifesto values ongoing customer collaboration throughout delivery, not just at kickoff, so this is wrong.
Why D is wrong: A heavyweight change-control gate favours process and documentation over individuals and interactions and responding to change, so although it feels disciplined it conflicts with the values here.
lock_openFree sampleProject Management Fundamentals and Core Conceptseasy
The Harbourline mobile banking programme has stable, well-understood requirements, a fixed regulatory deadline, and a client who wants the full scope defined and signed off before any build starts. The sponsor asks which development approach best fits these conditions. Which approach should the project manager recommend?
- AA predictive approach, planning scope, schedule, and cost in detail before execution beginscheck_circle Correct
- BAn adaptive approach, so the team can reprioritise the backlog every iteration as feedback arrives
- CAn incremental approach, so a usable subset of features is released at the end of each short cycle
- DA hybrid approach, combining predictive planning with adaptive delivery for the same requirements
A predictive life cycle suits work whose scope and requirements are well understood and fixed before execution begins. A predictive approach front-loads detailed planning of scope, schedule, and cost because the requirements are known and stable, which lets the team commit to a plan and a fixed deadline with confidence.
Why A is correct: Predictive life cycles fit stable, clearly defined requirements planned in full before work starts, which matches the fixed scope, signed-off requirements, and fixed deadline described here.
Why B is wrong: Adaptive approaches suit volatile requirements and frequent change, but this programme has stable, well-understood scope defined up front, so the flexibility adds overhead without benefit.
Why C is wrong: Incremental delivery is tempting because of the fixed deadline, but it is chosen to get working functionality into users' hands early, not because requirements are fully known and fixed at the outset.
Why D is wrong: Hybrid is useful when parts of the work are uncertain and parts are stable, but nothing here is described as uncertain, so blending approaches introduces complexity the situation does not call for.
More free CAPM practice questions, every answer explainedFrequently asked questions
- How many questions are on the CAPM exam?
- The PMI Certified Associate in Project Management (CAPM) exam has 150 (135 scored) questions and runs for 180 minutes. The format is multiple choice, closed book.
- What score do I need to pass CAPM?
- PMI does not publish a fixed pass mark for CAPM, so treat any "X%" figure you see elsewhere as unofficial. Examworthy gives you a per-domain readiness score so you can judge when you are ready across every domain.
- How much does the CAPM exam cost?
- The exam costs 300 USD to sit. Practising on Examworthy is free to start, and every answer is explained, right and wrong.
- Is there a CAPM practice exam?
- Yes. Examworthy's exam mode runs a timed CAPM practice exam (mock) paced to match the real exam, scored per domain so you can see exactly where you stand. Timed mocks are free with an account.
- How does Examworthy help me prepare for CAPM?
- Every practice question explains why the right answer is right and why each wrong one is wrong, mapped to the official blueprint domains. You learn the reasoning, not just the letter.
- Is Examworthy affiliated with PMI?
- No. Examworthy is not affiliated with or endorsed by PMI. Our questions are original, blueprint-aligned practice material; we never reproduce live exam items.
Examworthy is not affiliated with or endorsed by PMI. All questions are original, blueprint-aligned practice material. We never reproduce live exam items. CAPM and related marks belong to their respective owners.