CAPM domain - 17% of the exam

Predictive, Plan-Based Methodologies

Predictive, Plan-Based Methodologies is 17% of the PMI Certified Associate in Project Management (CAPM) exam. These are the objectives it covers, each with practice questions and worked explanations.

Objectives in this domain

Sample question from this domain

Free samplePredictive, Plan-Based Methodologieshard

A small project network has five activities. Activity A (3 days) and Activity B (6 days) both start the project. Activity C (8 days) follows A. Activity D (4 days) follows B. Activity E (5 days) starts only after both C and D finish, and E ends the project. Which path is the project's critical path?

  • AA to C to E, with a total duration of 16 days Correct
  • BB to D to E, with a total duration of 15 days
  • CA to C to E, with a total duration of 11 days
  • DB to D to E, with a total duration of 18 days
The critical path is the longest continuous path through the network, which determines the earliest possible project finish. Adding activity durations along each complete path gives A to C to E at 16 days and B to D to E at 15 days. The longest of these, 16 days, is the critical path because any delay to its activities delays the whole project.

Why A is correct: The critical path is the longest continuous path through the network. A to C to E sums to 3 plus 8 plus 5, which is 16 days, longer than the only other path B to D to E at 15 days, so it sets the earliest project finish and its activities have zero total float.

Why B is wrong: B to D to E is the near-critical path at 15 days and carries only 1 day of total float. It is tempting because it starts with the longest single activity, B at 6 days, but a longer path exists, so it is not critical.

Why C is wrong: This correctly names the longest path but miscalculates its length, most likely by dropping activity E from the sum. The path A to C to E actually totals 16 days, not 11, so the duration stated here is wrong.

Why D is wrong: This selects the near-critical path and also overstates its length, probably by adding an activity that is not on it. B to D to E totals 15 days, and in any case it is not the longest path, so it is not the critical path.

Other domains in this exam

See also the CAPM cert hub, the study guide, and the cheat sheet.

Examworthy is not affiliated with or endorsed by PMI. Original, blueprint-aligned practice material only.