CAPM domain - 17% of the exam

Predictive, Plan-Based Methodologies

Predictive, Plan-Based Methodologies is 17% of the CAPM exam. These are the objectives it covers, each with practice questions, with every answer explained.

The domain in numbers

48
Practice questions
4
Objectives
26
Medium
22
Hard

Where people go wrong

  • Compressing an activity that has float

    The wrong answers shorten work that sits off the critical path: the cheapest activity in the network, an activity on a shorter path, or an overlap of two non-critical activities. That only uses up float on a path that does not set the finish date. Only a critical-path activity shortens the project, and among those the cheapest is chosen. In one network, crashing the critical activity by 2 days takes its path from 15 days to 13, while the other path stays at 12, so the finish moves.

    See it in a sample question
  • Misreading free float, total float and the critical path

    The wrong answers treat free float and total float as equal, swap the two values, or set float to zero for an activity that is off the critical path. Others call the path with the most float, or the one holding the longest single activity, critical. The critical path is the longest summed path, and its activities carry zero total float. Free float is the successor's early start minus the activity's early finish, 15 minus 12 giving 3 days. Total float is late finish minus early finish, 18 minus 12 giving 6.

    See it in a sample question
  • Mixing up scope creep, gold plating and progressive elaboration

    The wrong answers swap these labels, and the deciding detail is who started the change. Gold plating is the team adding an unrequested extra on its own initiative, such as an animated dashboard theme. Scope creep is uncontrolled work added from outside the baseline, such as extra report formats or shelving racks asked for by a stakeholder or supervisor. Progressive elaboration only refines planned scope, so it never covers a new deliverable.

    See it in a sample question
  • Naming the wrong documents as the scope baseline

    The wrong answers build the baseline from genuine project documents that are not part of it. They offer the charter, stakeholder register and traceability matrix, the management plans, or a mix of the schedule and cost baselines. The scope baseline is the approved project scope statement, the WBS and the WBS dictionary. The schedule and cost baselines are separate, and the scope baseline changes only through formal change control.

    See it in a sample question
  • Inverting earned value formulas

    The wrong answers flip a subtraction or a ratio, or read a cost index as a schedule index. Cost variance is earned value minus actual cost, and schedule variance is earned value minus planned value. The cost performance index divides earned value by actual cost, 200,000 over 250,000 giving 0.80. The schedule performance index divides earned value by planned value, 90,000 over 75,000 giving 1.20. A negative variance means over budget or behind.

    See it in a sample question

Objectives in this domain

What to study

The official documents this domain's practice questions cite most.

Sample questions from this domain

Free samplePredictive, Plan-Based Methodologieshard

A predictive project is running late and the sponsor has directed the team to shorten the remaining schedule. The activities on the critical path have mandatory finish-to-start dependencies and cannot be performed in parallel, but the sponsor has approved additional budget and additional staff. Which schedule compression approach best fits these constraints?

  • AFast track by overlapping the critical path activities so they run concurrently.
  • BCrash a non-critical activity that has spare total float to reduce cost.
  • CCrash the critical path activities by adding the approved resources. Correct
  • DReduce the project scope and re-baseline the schedule to the new end date.
Crashing adds resources to shorten the schedule; fast tracking overlaps activities and needs discretionary, not mandatory, dependencies. Crashing adds resources to shorten critical path activities and suits a funded team facing mandatory dependencies, whereas fast tracking requires overlapping activities that only discretionary logic permits, which mandatory finish-to-start links forbid.

Why A is wrong: Fast tracking overlaps activities normally done in sequence, but these activities have mandatory finish-to-start dependencies and physically cannot overlap, so fast tracking is not available here.

Why B is wrong: Crashing a floated, non-critical activity spends money without shortening the project, because only the critical path drives the finish date and float elsewhere does not affect it.

Why C is correct: Crashing adds resources to critical path activities to shorten their duration, which fits a case where extra budget and staff are available and the mandatory dependencies rule out fast tracking.

Why D is wrong: Cutting scope changes what the project delivers rather than compressing the existing work, and re-baselining to a later date does not pull the finish in, so it is not a compression technique.

Free samplePredictive, Plan-Based Methodologieshard

Activity Q has an early finish on day 12. Its only successor, activity R, has an early start on day 15. Activity Q does not lie on the critical path, and the backward pass gives Q a late finish on day 18. Based on these figures, what are Q's free float and total float?

  • AFree float of 6 days and total float of 3 days
  • BFree float of 3 days and total float of 3 days
  • CFree float of 3 days and total float of 6 days Correct
  • DFree float of 0 days and total float of 6 days
Free float uses a successor's early start while total float uses an activity's own late finish, so the two values often differ. Free float equals the earliest start of the successor minus the early finish of the activity, 15 minus 12 equals 3. Total float equals the activity's late finish minus its early finish, 18 minus 12 equals 6. Different reference points produce different amounts of slack.

Why A is wrong: This swaps the two values. Free float looks at the successor's early start and equals 3 days, while total float uses the late finish and equals 6 days. The larger number is total float, so the figures are reversed here.

Why B is wrong: Treating free float and total float as equal is a frequent error. They coincide only when an activity's delay would immediately push its successor, which is not the case here, so the two values differ.

Why C is correct: Free float is the successor's early start minus Q's early finish, 15 minus 12, giving 3 days. Total float is Q's late finish minus its early finish, 18 minus 12, giving 6 days. The two measures answer different questions and correctly differ here.

Why D is wrong: Assuming free float is zero because Q is off the critical path is wrong. Free float is the successor early start minus Q's early finish, 15 minus 12, which is 3 days, not zero.

Free samplePredictive, Plan-Based Methodologiesmedium

Midway through the Ashford payroll migration, a business unit lead asks the developer directly to add two extra report formats, and the developer builds them without any change request or baseline update. What has occurred, and what is the most appropriate response?

  • AScope creep, so the project manager should route the added reports through the change control process Correct
  • BProgressive elaboration, so the project manager should record the added detail and continue as planned
  • CGold plating, so the project manager should ask the developer to remove the extra reports at once
  • DApproved scope change, so the project manager should update the WBS and inform the sponsor afterwards
Adding work outside the scope baseline without a change request is scope creep and must be routed through change control. Scope creep is uncontrolled expansion of scope without adjustments to time, cost, and resources; the disciplined response is to evaluate the request through integrated change control so its impact is assessed and it is formally approved or rejected rather than silently absorbed.

Why A is correct: Correct: adding work outside the baseline without a change request is scope creep, and the appropriate response is to bring the addition through the integrated change control process for evaluation and approval or rejection.

Why B is wrong: Progressive elaboration refers to refining planned scope in increasing detail over time, not adding new deliverables outside the baseline, so labelling an uncontrolled addition this way excuses the real problem.

Why C is wrong: Gold plating is the team adding unrequested extras on its own initiative; here a stakeholder requested the reports, so the situation is uncontrolled change from outside, not team-initiated embellishment.

Why D is wrong: No change request was raised or approved, so treating the work as an approved change skips the control step that distinguishes managed change from uncontrolled growth.

Free samplePredictive, Plan-Based Methodologiesmedium

As the Cedar Grove clinic fit-out enters planning, the project manager wants to establish the approved scope baseline against which future change will be measured. Which set of components together make up the scope baseline?

  • AThe requirements documentation, the requirements traceability matrix, and the stakeholder register
  • BThe project charter, the scope management plan, and the requirements management plan
  • CThe scope statement, the schedule baseline, and the cost baseline together as one integrated set
  • DThe project scope statement, the work breakdown structure, and the WBS dictionary Correct
The scope baseline is the approved scope statement, WBS, and WBS dictionary, changed only through formal change control. These three components together fix what is in and out of scope: the scope statement describes the deliverables and boundaries, the WBS decomposes them, and the WBS dictionary details each component, giving a stable reference for measuring and controlling change.

Why A is wrong: These are useful scope-related records produced during requirements collection, but they are inputs and supporting tools rather than the approved baseline that scope is measured against.

Why B is wrong: These documents authorise the project and describe how scope and requirements will be managed, yet they do not themselves define the approved deliverables, so they are not the scope baseline.

Why C is wrong: This mixes three separate baselines; the schedule and cost baselines are distinct from the scope baseline, so combining them misstates what the scope baseline specifically contains.

Why D is correct: Correct: the scope baseline is the approved version of the scope statement, the WBS, and the WBS dictionary, and it can be changed only through formal change control.

Free samplePredictive, Plan-Based Methodologieshard

The Meridian Data Centre migration reports earned value of 200,000 euros and actual cost of 250,000 euros at the halfway review, against a budget at completion of 500,000 euros. What is the cost performance index, and what does it indicate about the work so far?

  • A0.80, indicating the project earns 0.80 euros of value for each euro that it spends. Correct
  • B1.25, indicating the project earns 1.25 euros of value for each euro that it spends.
  • C0.80, indicating the project is running ahead of its planned schedule.
  • D1.25, indicating strong cost efficiency across the work completed to date.
The cost performance index is earned value divided by actual cost, and a value below one means poor cost efficiency. The cost performance index divides earned value by actual cost, so 200,000 over 250,000 equals 0.80, and a result under one means the project is delivering less than a full unit of value for every unit of cost, which points to a cost overrun.

Why A is correct: The cost performance index is earned value divided by actual cost, so 200,000 over 250,000 equals 0.80; a value below one means each euro spent has returned less than a euro of work, signalling an overrun.

Why B is wrong: This inverts the ratio to actual cost divided by earned value; the cost performance index is earned value over actual cost, so the figure should be below one, not above it.

Why C is wrong: The value 0.80 is correct but the meaning is wrong; the cost performance index reports cost efficiency, while schedule position is measured by the schedule performance index, which needs planned value.

Why D is wrong: This both inverts the ratio and misreads it as good news; dividing earned value by actual cost gives 0.80, which shows poor efficiency, so 1.25 is doubly wrong.

Other domains in this exam

See also the CAPM cert hub, the study guide, and the cheat sheet.

Examworthy is not affiliated with or endorsed by PMI. Original, blueprint-aligned practice material only.