On the Harbourgate fit-out project, the project manager has just finished baselining scope with the sponsor. A team member asks which set of documents makes up the approved scope baseline. Which combination correctly identifies the scope baseline?
- AThe project charter, the stakeholder register, and the requirements traceability matrix
- BThe approved project scope statement, the schedule baseline, and the cost baseline
- CThe approved project scope statement, the work breakdown structure, and the WBS dictionary Correct
- DThe requirements management plan, the scope management plan, and the change log
Why A is wrong: These are genuine scope-related inputs and outputs, but the charter and stakeholder register sit outside the scope baseline and the traceability matrix links requirements rather than forming the baseline itself.
Why B is wrong: This mixes three separate baselines together; the schedule and cost baselines are distinct from the scope baseline and are not part of its definition.
Why C is correct: The scope baseline is the approved version of the scope statement, the WBS, and the WBS dictionary, and changes to it are controlled through formal change control.
Why D is wrong: These are planning and control artefacts that guide how scope is managed, but they describe the process rather than defining the approved scope content itself.