During a hybrid infrastructure project, newly imposed trade restrictions block the import of a hardware component the current design depends on. The project manager has just been notified of the restriction. What should the project manager do FIRST?
- ADirect the procurement lead to source any available substitute component at once so the schedule is not disturbed.
- BRecord the restriction in the issue register and continue with planned work until the next phase-gate review.
- CEscalate to the sponsor with a request to extend the deadline before any alternatives have been examined.
- DAnalyse how the restriction affects scope, cost and schedule, then evaluate the options with the team and stakeholders. Correct
Why A is wrong: Speed feels protective of the schedule, but committing to a substitute before understanding the effect on scope and design risks locking in an unsuitable or non-compliant choice.
Why B is wrong: Logging the issue is part of good practice, yet deferring analysis to a later gate lets a change that blocks the design ripple unmanaged through scope and schedule.
Why C is wrong: Asking for time seems responsible, but requesting a deadline change before assessing options presents the sponsor with a solution rather than an analysed impact.
Why D is correct: A geopolitical restriction is an external change, so the project manager first surveys its impact on scope and constraints and works options through with the team and stakeholders before deciding a response.