PMP domain - 42% of the exam

People

People is 42% of the PMI Project Management Professional (PMP) exam. These are the objectives it covers, each with practice questions and worked explanations.

Objectives in this domain

Sample question from this domain

Free samplePeoplemedium

A newly formed agile team is midway through its first two sprints and members keep interrupting one another in stand-ups, with two engineers openly disagreeing about who owns integration testing. Delivery has slowed and morale is dipping. Applying servant leadership, what should the project manager do FIRST?

  • AFacilitate the team in agreeing a set of ground rules covering communication, decision-making, and how work is shared. Correct
  • BAssign each disputed task to a named individual and publish a fixed responsibility list so the arguments stop immediately.
  • CEscalate the conflict to the sponsor and ask for a ruling on which engineer should lead integration testing.
  • DWait for the team to settle by itself over the coming sprints, since storming behaviour usually passes without intervention.
A servant leader helps a storming team agree its own ground rules rather than imposing assignments or escalating. Ground rules set team-owned expectations for behaviour and collaboration, which resolves the storming-stage friction at its source and lets the self-organising team move toward performing without command-and-control intervention.

Why A is correct: The friction is typical of the storming stage, and a servant leader responds by helping the team surface and agree its own ground rules, which gives shared, durable norms the team owns rather than a manager's edict.

Why B is wrong: Imposing assignments is a command-and-control reflex that removes the self-organising team's ownership; it may quiet the symptom but does not address the missing agreement on how the team will work together.

Why C is wrong: Escalating a normal team-formation dispute is premature and undermines the team's ability to self-organise; the sponsor is not close enough to the work to make a better call than the team can.

Why D is wrong: Storming does often pass, but passive waiting while delivery and morale slide neglects the servant leader's duty to remove impediments and help the team reach performing sooner.