A hybrid project will hand a new analytics platform to a business operations group at go-live. During planning the project manager learns that the operations staff have never used a tool of this kind, and the sponsor assumes they will simply pick it up on the day. The project manager is responsible for ensuring stakeholders are adequately trained. What should the project manager do FIRST?
- ARecord in the risk register that the group may struggle, and revisit the training question only if problems appear after go-live.
- BBook every operations staff member onto the vendor's full multi-day certification course to be certain no skill is missed.
- CAsk the sponsor to sign a statement accepting responsibility for any shortfall in the operations group's readiness at go-live.
- DAssess the operations group's current competencies against what the platform requires, then plan targeted training to close the gap before go-live. Correct
Why A is wrong: Logging a risk is reasonable housekeeping, but waiting for problems to surface after go-live is reactive and skips the project manager's duty to prepare stakeholders in advance.
Why B is wrong: Maximum training sounds thorough, but committing to a full certification without assessing need is gold-plating that wastes budget and time the assessment might show are unnecessary.
Why C is wrong: Transferring blame to the sponsor may feel protective, but it dodges the project manager's own accountability for training and does nothing to make the stakeholders competent.
Why D is correct: Correct: identifying the skills gap first lets the project manager plan proportionate, targeted training so stakeholders are genuinely ready, which is the responsibility the objective describes.