A predictive infrastructure project has a budget at completion (BAC) of GBP 800,000. At the current status date the planned value (PV) is GBP 300,000, the earned value (EV) is GBP 240,000, and the actual cost (AC) is GBP 320,000. The project manager has just calculated a cost performance index of 0.75 and a schedule performance index of 0.80. What should the project manager do FIRST?
- ASubmit a change request for an extra GBP 266,667 to fund the forecast overrun and carry on with the plan unchanged.
- BInvestigate the root causes of the cost and schedule variances before recommending any corrective action. Correct
- CCrash the critical path by adding resources so that the schedule performance index is brought back up to 1.0.
- DRe-baseline the schedule and budget so that future performance is measured against more achievable targets.
Why A is wrong: The forecast overrun figure is plausible because BAC divided by the cost performance index gives an estimate at completion of about GBP 1,066,667, but throwing budget at the problem before understanding its cause treats a symptom and is premature.
Why B is correct: Earned value indices signal that variances exist but not why; the correct first step is variance analysis to find the drivers, so that any later corrective action addresses the real cause rather than a symptom.
Why C is wrong: Crashing looks responsive to the poor schedule index, yet applying a corrective action before diagnosing why work is behind risks spending money on the wrong problem and worsening the cost overrun.
Why D is wrong: Re-baselining seems to restore control, but changing the baseline to hide a variance masks the problem and is a last resort reserved for approved changes, not an opening response to unexplained slippage.