A project sponsor has approved a project charter and asks the newly assigned project manager to start delivery planning for a mid-size predictive project. The organisation has assets from similar past projects, including plan templates, lessons learned, and a change management procedure. Which action best reflects the integrating purpose of the planning effort?
- ADraft the schedule and budget first and treat the other subsidiary plans as optional additions if time allows later in execution.
- BAdopt the past project's full plan set unchanged so the new project inherits a proven, ready-made project management plan.
- CWait for the sponsor to specify which subsidiary plans are needed before beginning any planning work.
- DDevelop the subsidiary plans and tailor the organisational assets to this project, then integrate them into one consistent project management plan. Correct
Why A is wrong: Prioritising the schedule and budget feels efficient, but treating the other subsidiary plans as optional leaves the project management plan incomplete and unintegrated, which is what planning is meant to prevent.
Why B is wrong: Reusing a proven plan set wholesale is tempting given the available assets, but it skips tailoring to this project's context and mistakes copying for the integration and fit that planning requires.
Why C is wrong: Waiting for direction seems collaborative, but selecting and integrating the subsidiary plans is the project manager's planning responsibility, so pausing for the sponsor to decide is an unnecessary delay.
Why D is correct: Correct. Planning integration draws on organisational process assets, tailors them to the project, and consolidates the subsidiary plans into a single coherent project management plan that governs execution.